Lockheed Martin So Sick of Stupid MTA Surveillance Contract

It's been more than seven years since the attacks of September 11th inspired the MTA to beef up security in the transit system, but a massive effort to improve surveillance underground is still incomplete. Back in 2005, the authority sealed a $212 million deal with Lockheed Martin to install 1,000 video cameras and 3,000 motion sensors, as well as enable cellphone service in 277 underground stations. Today the Times reports that large parts of the project are not "scheduled" to be completed until September, and that estimate doesn't even include parts of the under-river tunnels used by the subway and the Long Island Rail Road. The project was supposed to be done last August.

Now Lockheed Martin has asked a federal judge to release it from the project, and blames the numerous delays on the MTA, arguing that the authority has refused to shut down the tunnels so they could install the equipment. But the MTA says the system Lockheed installed is a big fat FAIL, and the state comptroller reported last spring [pdf] that 400 of 1,400 software elements in the system did not pass tests. The software connected to cameras is supposed to detect an unattended object left on a station platform, and then alert law enforcement.

In a statement, MTA officials rubbed Lockheed's nose in it, saying, "It has taken longer than expected because of Lockheed’s inability to resolve certain critical system issues." The cost of the project has now swollen to $453 million, of which the company's been paid about $250 million so far. According to the Post, Lockheed is claiming losses of $3 million a month while "key personnel" languish on the stalled project, and it intends to file a separate suit to recover damages.

Contact the author of this article or email tips@gothamist.com with further questions, comments or tips.

Comments [rss]

  • Nyctini11

    What's the rush?? it's not like women are getting raped down there, oh wait

  • pinball29

    How does 212 million turn into 453 million because of a 13 month delay in a project signed for in 2005.

    This project should be independently investigated and audited, just like the ENTIRE MTA. But of course, that will never happen when they can simply raise fares and cry poverty while stealing untold millions.

  • Think2wice

    Oh, as a multi-state public benefit corporation I'd gleefully like to see them testify before Congress.

  • drewo

    Eisenhower: "“We will bankrupt ourselves in the vain search for absolute security.”

  • gothamguy

    How long after this is finished and paid for until someone mentions that wiring the stations for cell coverage makes it easier for someone to detonate a device triggered by a mobile phone, like they do with IED's in Iraq?

  • citizenerased

    Dear Lockheed Martin,

    Welcome to our world

  • poopmast

    Doesnt it make sense to implement the system first and work out the kinks once a functional testbed system is in place?

    I've never heard of QA work done at the same time of implementing.

    Wait this is the MTA.

  • Politburo

    The software can be written and tested before the cameras are actually installed.

  • Politburo

    While I'm completely sure that the MTA is fucking this up, the client is not responsible for your staffing decisions.